Natex Exterior 01 - Day_edited.jpg

NATEX

100% SOLD OUT

See below for construction updates. 

Luxury Student Apartments. Liverpool U.K.

  • From £85,000

  • 9% Net Yield per annum guaranteed for 5 years

  • Up to 4% interest on deposited funds

  • 7 Universities with 60,000 students within 1 kilometre

  • No expense until year 6

  • All units sold fully furnished

  • Fully managed 

 

Construction Update

MAY 2021

Planned works this period :
Block A

  • Complete the installation windows to up to level 14

  • Complete the installation of curtain walling to level 15

  • Complete the roof installation   

  • Complete the installation of 1st fixed partitions to level 13 and 14

  • Continue 1st fix M&E installation on levels 13 – 15

  • Continue plastering, levels 3 – 6

  • Commence floor finishes

  • Commence decoration

  • Commence FF&E instalation

Block B

  • Complete decking & concrete floors

  • Commence the roof installation

  • Continue with the SFS and boarding

  • Commence the window installation

  • Commence the partitions 1st fix ​

Works Completed Last Period

Block A

  • The Steel frame of block A is complete and the roofing decking has been installed.

  • Mast climbers and hoists continue to operate feeding the floor plates.

  • Pods have been delivered and installed

  • Roofing materials have been delivered and loaded out and roof coverings are ongoing.

  • The external SFS has continued and is now complete with boarding now largely complete to level 14.

  • The Curtain walling to level 15 is now being installed

  • Windows up to level 13 have been installed

  • Partitions are now 1st fixed to up to level 12, levels 1 – 4 have been second side boarded and are complete

  • Skimming is ongoing to levels 1 and 2

  • 1st fix M&E installation progressed well to level 12 and 2nd fix has commenced behind level 1 plastering

Block B

  • Structural steelwork to block B is complete

  • The decking installation continues to block has one small area to complete on level 9

  • Concrete floors have been poured into the first half of the building. They are poured up to level 7 on the send half of the building

  • SFS and board has commenced on levels 1 – 4,

  • Builder work holes and setting out has commenced for the internal M&E services

  • J-Safe edge protection is being progressively installed as the frame progresses

  • Mastclimber bases have been installed.

  • The site continues to work under social distancing measures which are working well.

Further updates and images are available on request by contacting us using the form at the bottom of this page.

 
 
 

CONTACT US


Contact JP Knight today

Your  information is safe with us. We will never share it with anyone else.

We look forward to hearing from you.


Complete our subscribe form below to be kept up to date with new products. 

Thanks for submitting!